A. 10 days
B. 5 days
C. 3 days
D. None of these
🧠 Explanation (Math):
Given: 10 persons in 20 days; now 20 persons with twice efficiency Step 1: Work $=10times20=200$ person-days. Step 2: Effective persons $=20times2=40$. Step 3: Time $=200/40=5$ days. Final Answer: 5 days